Project activities and timeframes

The Surat Basin Rail Joint Venture is striving to investigate and progress the Project with the following key milestones by the indicative dates set out below:

Key project milestones

Appoint engineering consultancy to plan and design railway July 2007 Completed
Finalise preferred route between Wandoan and Banana November 2007 Completed
Submit Initial Advice Statement (IAS) to the Coordinator-General January 2008 Completed
Submit Environmental Impact Statement (EIS) to the Coordinator-General for public comment (available for comment until 5pm Monday 23 March 2009) Early 2009 Completed
Preparation of the Supplementary EIS Report Mid 2009 Completed – to be submitted in Nov 2009
Submit a Business Case to the State. September 2009 Completed
Agree with the Queensland Government on the principles for a development agreement. September 2009 Draft principles agreed
Coordinator-General to prepare a report evaluating the complete EIS and providing a decision on the Surat Basin Rail's approval. June 2010 Future stage

* All time frames are indicative only. The ongoing feasibility of the Project will be assessed at the end of each stage of the Project and whether the Project progresses to the next stage will depend on the outcome of that assessment.